Requesting a three-phase connection: how it works

Add an EV charger, a heat pump or induction cooking, and your single-phase connection soon reaches its limit. Upgrading to three-phase is then the logical step. Here you can read exactly how the application works: who does what, which steps you take and how long it takes.

Updated on 2 July 20267 min read

In brief

The short answer

You request a three-phase connection from your grid operator, in Noord-Brabant that is usually Enexis, via mijnaansluiting.nl. The grid operator upgrades the connection up to your meter; a certified electrician then adapts the meter cabinet and fuse box. Allow a lead time of several weeks to months, partly because of the pressure on the grid.

  • The grid operator (in Brabant usually Enexis) upgrades the connection; you apply for it via mijnaansluiting.nl.
  • A certified electrician prepares the meter cabinet and fuse box for three-phase.
  • Three-phase is needed for heavy or simultaneous use: an EV charger, heat pump and induction cooking together.
  • The lead time runs from several weeks to several months, certainly with grid congestion.
  • You pay the grid operator one-off and periodic costs, plus the electrician for the work.

Step by step

How to request a three-phase connection

From uncertainty to a working connection: these are the steps. The application with the grid operator and the electrician's work partly run in parallel, so plan them in good time.

  1. 1

    Work out whether you need three-phase

    Add up your heavy users: EV charger, heat pump, induction hob, home battery. If you use them at the same time, single-phase is often too tight. Not sure? Have an electrician look at your current connection and usage.

  2. 2

    Apply for the upgrade with your grid operator

    Arrange the application via mijnaansluiting.nl. You choose the capacity you want (for example 3x25A or 3x35A) and your address. Your grid operator, in Brabant usually Enexis, sends a quote with the costs and a schedule.

  3. 3

    Have a certified electrician prepare the meter cabinet

    The grid operator only upgrades up to the meter. Everything beyond it is for the electrician: adapting or replacing the fuse box, fitting the right RCDs and circuits, so the box can safely handle the new capacity.

  4. 4

    The grid operator carries out the connection

    On the scheduled date the grid operator actually upgrades the connection and, if needed, fits a new meter. This only happens once the application is complete and, where required, the meter cabinet is ready.

  5. 5

    Testing and handover

    The electrician tests the installation, checks the circuits and hands it over neatly to NEN 1010. After that you can safely load your EV charger, heat pump or induction hob without the fuses tripping.

Single-phase or three-phase: what is the difference?

Most older homes have a single-phase connection. That means all your power comes into the house through a single phase, usually 1x35A or 1x40A. For an ordinary household that was ample for a long time: lighting, a few appliances, a gas hob. But as soon as you add heavier users, you quickly reach the ceiling of what that one phase can handle.

With a three-phase connection the power comes in through three phases. You can spread the load across those three, which lets you draw much more power at once without overloading. An EV charger that charges fast, a heat pump working hard on a cold morning and induction cooking at the same time: that calls for the extra headroom. Three-phase is therefore not a luxury but a basic requirement for a home that is going electric.

Worth knowing: three-phase is about how much you can use at once, not automatically about higher power use or a bigger bill. Your energy use depends on what your appliances actually draw. The connection only determines the maximum simultaneous load.

When do you really need three-phase?

The rule of thumb: when several heavy users get in each other's way. A single EV charger that charges slowly can sometimes just about manage on single-phase. But if you want fast charging, or add a heat pump, single-phase becomes tight. And if you also use those things at the same time as induction cooking, the main fuse will trip sooner or later.

In practice you mainly see three-phase come up with these combinations: an EV charger you want to charge at home with more power, a heat pump for your heating, induction cooking instead of gas, and sometimes a home battery you want to charge and discharge quickly. On their own they are often still manageable; together they are not.

Not sure whether you really need it? Have a certified electrician look at your situation before you apply for anything. Sometimes a smart charging strategy or load balancing turns out to be enough, and sometimes upgrading is unavoidable. Better to know that beforehand than to get stuck halfway.

Who does what: grid operator and electrician

A three-phase connection involves two parties, and it helps to know early who does what. The grid operator is responsible for everything up to and including your meter: the cable from the grid, the connection itself and the meter. In Noord-Brabant the grid operator in most municipalities is Enexis. You apply for the upgrade with them via mijnaansluiting.nl, the central point for this kind of application.

Everything behind the meter is for a certified electrician. They make sure your fuse box is ready for three-phase: the right main switch, 30 mA RCDs, the load neatly spread across the three phases and circuits that match your new users. Often that means a new or adapted fuse box, so it can safely carry the extra capacity.

The two strands interlock. The grid operator only upgrades once the application is complete, and the work in the meter cabinet has to be right before you can load everything. An electrician who knows the region coordinates the two: they know how the application runs, factor in the waiting time at Enexis and make sure the box is ready on time. That way you do not have to translate between two parties.

Lead time and costs: what to bear in mind

You do not arrange a three-phase connection in an afternoon. From application, allow several weeks to several months, depending on how busy the grid operator is and the situation on site. Part of that time is planning and admin, part is the actual work. So apply in good time, especially if your renovation or your EV charger has a deadline.

Pressure on the grid plays a part. In many places in Noord-Brabant there is grid congestion: the grid is full, and that can delay applications. For an ordinary household upgrade the impact is usually smaller than for large consumers, but it can still stretch the lead time. Bear that in mind when you plan.

There are two sides to the costs. The grid operator charges one-off connection costs for the upgrade, and after that you pay periodic costs that go with a heavier connection (the standing charge rises with the capacity). On top of that you pay the certified electrician for the work on your meter cabinet and fuse box. What it comes to for you depends on your current box and the capacity you want. Ask for a quote for the installation and check the current rates with the grid operator, so you know where you stand beforehand.

At a glance

Who does what?

A three-phase connection needs both the grid operator and the certified electrician. This is how the work is divided.

TaskGrid operator (Enexis)Certified electrician
Upgrade applicationHandles the application via mijnaansluiting.nlAdvises beforehand on the right capacity
Cable and connection up to the meterYes, this is their workNo
Fitting or replacing the meterYesNo
Adapting the meter cabinet and fuse boxNoYes, adapts the box for three-phase
Circuits and RCDsNoYes, to NEN 1010
Testing and handing over the installationNoYes, tests and hands over

In most Brabant municipalities Enexis is the grid operator. Not sure who yours is? You can check that based on your postcode.

Why Brabant Elektra

Prefer to have a professional take a look?

Our certified electricians work across all of Noord-Brabant to NEN 1010, with a fixed price upfront and a 2-year work guarantee. Certified, insured and straightforwardly professional.

4,8· 312 reviews
Certified installer2-year guaranteeInsured
The Brabant Elektra team: eight qualified engineers in company workwear

Frequently asked questions

Good to know

You apply for the upgrade with your grid operator via mijnaansluiting.nl, the central point. In most Brabant municipalities Enexis is your grid operator. You give your address and the capacity you want, after which you receive a quote and a schedule. The work on your meter cabinet and fuse box you arrange separately with a certified electrician.
With single-phase all the power comes in through a single phase; with three-phase through three phases. With three-phase you spread the load and can draw much more power at once. That is needed when you use heavy users such as an EV charger, heat pump and induction hob at the same time. It is about simultaneous power, not automatically about a higher total consumption.
Mainly when several heavy users get in each other's way: an EV charger that charges fast, a heat pump and induction cooking, especially in combination. On their own it sometimes still works on single-phase; together the main fuse fills up. Have a certified electrician look at your situation before you apply, because sometimes smart load balancing is enough.
From application, allow several weeks to several months. The exact lead time depends on how busy the grid operator is and the situation at your home. Because of grid congestion in parts of Noord-Brabant it can take longer. So apply in good time, especially if your renovation or EV charger has a deadline.
You pay the grid operator one-off connection costs for the upgrade and then periodic costs that go with a heavier connection. On top of that you pay the certified electrician for the work on your meter cabinet and fuse box. What it comes to for you depends on your current box and the capacity you want. Ask for a quote and check the current rates with the grid operator.
No. The grid operator upgrades the connection up to and including the meter and, if needed, fits a new meter. Everything beyond it, so your fuse box, the circuits, RCDs and the split across the phases, is work for a certified electrician. They make sure the box can safely handle the new capacity.
Yes, and that is often sensible. The application with the grid operator and the work on your meter cabinet partly run in parallel. The grid operator only upgrades once the application is complete, and the box has to be right before you can load everything. An electrician who knows the region coordinates both strands, so you do not wait unnecessarily.
Not by itself. Your energy use depends on what your appliances actually draw, not on the number of phases. The standing charge for your connection does rise as the capacity gets heavier, so the periodic costs of the connection go up a little. Check the current rates with your grid operator for an exact picture.

Service area

An electrician near you

From Eindhoven to Breda and from Den Bosch to Tilburg: our certified electricians come to you, with a fixed price upfront.

Sorted directly

Want your connection upgraded to three-phase?

We arrange the application with the grid operator and prepare your meter cabinet for three-phase, safely to NEN 1010 and with a fixed price upfront. Call us or request a quote, and we will look together at what you need.

4,8· 312 reviews
Certified installer2-year guaranteeInsured