In brief
The short answer
You request a three-phase connection from your grid operator, in Noord-Brabant that is usually Enexis, via mijnaansluiting.nl. The grid operator upgrades the connection up to your meter; a certified electrician then adapts the meter cabinet and fuse box. Allow a lead time of several weeks to months, partly because of the pressure on the grid.
- The grid operator (in Brabant usually Enexis) upgrades the connection; you apply for it via mijnaansluiting.nl.
- A certified electrician prepares the meter cabinet and fuse box for three-phase.
- Three-phase is needed for heavy or simultaneous use: an EV charger, heat pump and induction cooking together.
- The lead time runs from several weeks to several months, certainly with grid congestion.
- You pay the grid operator one-off and periodic costs, plus the electrician for the work.
Step by step
How to request a three-phase connection
From uncertainty to a working connection: these are the steps. The application with the grid operator and the electrician's work partly run in parallel, so plan them in good time.
- 1
Work out whether you need three-phase
Add up your heavy users: EV charger, heat pump, induction hob, home battery. If you use them at the same time, single-phase is often too tight. Not sure? Have an electrician look at your current connection and usage.
- 2
Apply for the upgrade with your grid operator
Arrange the application via mijnaansluiting.nl. You choose the capacity you want (for example 3x25A or 3x35A) and your address. Your grid operator, in Brabant usually Enexis, sends a quote with the costs and a schedule.
- 3
Have a certified electrician prepare the meter cabinet
The grid operator only upgrades up to the meter. Everything beyond it is for the electrician: adapting or replacing the fuse box, fitting the right RCDs and circuits, so the box can safely handle the new capacity.
- 4
The grid operator carries out the connection
On the scheduled date the grid operator actually upgrades the connection and, if needed, fits a new meter. This only happens once the application is complete and, where required, the meter cabinet is ready.
- 5
Testing and handover
The electrician tests the installation, checks the circuits and hands it over neatly to NEN 1010. After that you can safely load your EV charger, heat pump or induction hob without the fuses tripping.
Single-phase or three-phase: what is the difference?
Most older homes have a single-phase connection. That means all your power comes into the house through a single phase, usually 1x35A or 1x40A. For an ordinary household that was ample for a long time: lighting, a few appliances, a gas hob. But as soon as you add heavier users, you quickly reach the ceiling of what that one phase can handle.
With a three-phase connection the power comes in through three phases. You can spread the load across those three, which lets you draw much more power at once without overloading. An EV charger that charges fast, a heat pump working hard on a cold morning and induction cooking at the same time: that calls for the extra headroom. Three-phase is therefore not a luxury but a basic requirement for a home that is going electric.
Worth knowing: three-phase is about how much you can use at once, not automatically about higher power use or a bigger bill. Your energy use depends on what your appliances actually draw. The connection only determines the maximum simultaneous load.
When do you really need three-phase?
The rule of thumb: when several heavy users get in each other's way. A single EV charger that charges slowly can sometimes just about manage on single-phase. But if you want fast charging, or add a heat pump, single-phase becomes tight. And if you also use those things at the same time as induction cooking, the main fuse will trip sooner or later.
In practice you mainly see three-phase come up with these combinations: an EV charger you want to charge at home with more power, a heat pump for your heating, induction cooking instead of gas, and sometimes a home battery you want to charge and discharge quickly. On their own they are often still manageable; together they are not.
Not sure whether you really need it? Have a certified electrician look at your situation before you apply for anything. Sometimes a smart charging strategy or load balancing turns out to be enough, and sometimes upgrading is unavoidable. Better to know that beforehand than to get stuck halfway.
Who does what: grid operator and electrician
A three-phase connection involves two parties, and it helps to know early who does what. The grid operator is responsible for everything up to and including your meter: the cable from the grid, the connection itself and the meter. In Noord-Brabant the grid operator in most municipalities is Enexis. You apply for the upgrade with them via mijnaansluiting.nl, the central point for this kind of application.
Everything behind the meter is for a certified electrician. They make sure your fuse box is ready for three-phase: the right main switch, 30 mA RCDs, the load neatly spread across the three phases and circuits that match your new users. Often that means a new or adapted fuse box, so it can safely carry the extra capacity.
The two strands interlock. The grid operator only upgrades once the application is complete, and the work in the meter cabinet has to be right before you can load everything. An electrician who knows the region coordinates the two: they know how the application runs, factor in the waiting time at Enexis and make sure the box is ready on time. That way you do not have to translate between two parties.
Lead time and costs: what to bear in mind
You do not arrange a three-phase connection in an afternoon. From application, allow several weeks to several months, depending on how busy the grid operator is and the situation on site. Part of that time is planning and admin, part is the actual work. So apply in good time, especially if your renovation or your EV charger has a deadline.
Pressure on the grid plays a part. In many places in Noord-Brabant there is grid congestion: the grid is full, and that can delay applications. For an ordinary household upgrade the impact is usually smaller than for large consumers, but it can still stretch the lead time. Bear that in mind when you plan.
There are two sides to the costs. The grid operator charges one-off connection costs for the upgrade, and after that you pay periodic costs that go with a heavier connection (the standing charge rises with the capacity). On top of that you pay the certified electrician for the work on your meter cabinet and fuse box. What it comes to for you depends on your current box and the capacity you want. Ask for a quote for the installation and check the current rates with the grid operator, so you know where you stand beforehand.
At a glance
Who does what?
A three-phase connection needs both the grid operator and the certified electrician. This is how the work is divided.
| Task | Grid operator (Enexis) | Certified electrician |
|---|---|---|
| Upgrade application | Handles the application via mijnaansluiting.nl | Advises beforehand on the right capacity |
| Cable and connection up to the meter | Yes, this is their work | No |
| Fitting or replacing the meter | Yes | No |
| Adapting the meter cabinet and fuse box | No | Yes, adapts the box for three-phase |
| Circuits and RCDs | No | Yes, to NEN 1010 |
| Testing and handing over the installation | No | Yes, tests and hands over |
In most Brabant municipalities Enexis is the grid operator. Not sure who yours is? You can check that based on your postcode.
Read also
Read on and arrange it
Already know what you need, or want to read up first? These are the most common next steps.
Why Brabant Elektra
Prefer to have a professional take a look?
Our certified electricians work across all of Noord-Brabant to NEN 1010, with a fixed price upfront and a 2-year work guarantee. Certified, insured and straightforwardly professional.

Frequently asked questions
Good to know
Service area
An electrician near you
From Eindhoven to Breda and from Den Bosch to Tilburg: our certified electricians come to you, with a fixed price upfront.
Service area
Across Noord-Brabant
From major cities to smaller towns, active in:
Want your connection upgraded to three-phase?
We arrange the application with the grid operator and prepare your meter cabinet for three-phase, safely to NEN 1010 and with a fixed price upfront. Call us or request a quote, and we will look together at what you need.